Report on completed construction works in quarter LEGEND. on 31.12.2013.

 
Report on completed construction works in quarter LEGEND. on 31.12.2013.
 
There has been set a placement of concrete construction in the pool of SPA complex. The works on the main electricity substation installation have also been started. Currently preparation works for the winter period are being implemented.
 
Villa Dietrich 
Placement of concrete construction on the four floors of the building by the mentioned deadline has been finalised. Besides, metal roofing frameworks have been assembled and engineering networks have been connected to the building. Now distributing of internal engineering networks has been started, as well as the works on formwork installation and roof slab reinforcement, and construction of the walls between apartments.
 
Villa Hemingway 
The works on 0-cycle construction have been implemented on this site. Currently, construction of the building framework is being carried over.
 
Villa Tiffany 
At this site, the works on building zero cycle renovation are being carried out now.
 
Villa Churchill 
There the frame construction has been completed and all utility networks have been laid on to the building by the mentioned date. As on now there has been started distributing of internal engineering networks, alongside with the finishing works and works on construction of walls between apartments.
 
Villa Hepburn 
Placement of concrete frame of two floors and walls of the third floor has been launched. Currently the preparation works for placement of concrete construction on third floor are being conducted. Besides, there has been started distributing of internal engineering networks at the site.